Optimizing shutdown schedule
A waste treatment system required more planned downtime than its primary manufacturing
process. During the annual waste treatment shutdown, the waste storage tank would
first fill and then shut down the plant. A RonaMax simulation model was used to
develop a mini-shutdown schedule that minimized plant downtime associated with waste
treatment outtages. The model predicted the incremental production and waste
tank level as a function of
 | Equipment failures |
 | Shutdown schedule, and |
 | The time it took to bring the units up and down. |
Optimizing the waste treatment shutdown schedule ultimately resulted in 7 more days of production.
| |
|